View Original Article

Zargon Oil & Gas Ltd. Sanctions Little Bow ASP Tertiary Recovery Project Construction, Provides an Operational Update, Provides 2013 Guidance and Releases 2012 Year End Reserves

February 20, 2013 5:23 PM
BOE Report Staff

CALGARY, ALBERTA–(Marketwire – Feb. 20, 2013) – Zargon Oil & Gas Ltd. (the “Company” or “Zargon”) (TSX:ZAR) (TSX:ZAR.DB) is pleased to announce the sanctioning of the construction of the Little Bow Alkaline Surfactant Polymer (“ASP”) tertiary recovery facility, provide an operational update, provide 2013 guidance and report its 2012 year end reserves. Zargon intends to release its 2012 audited financial results on March 12, 2013, after market close.

LITTLE BOW ASP PROJECT SANCTIONING:

  • Zargon is sanctioning the construction of its tertiary recovery ASP oil exploitation project at the Little Bow oil property in Southern Alberta. This ASP project entails the injection of large volumes of a dilute chemical solution into a partially depleted oil reservoir to recover incremental oil reserves. With sanctioning, phases 1 and 2 of the Little Bow ASP project will be Canada’s ninth operational ASP project. For a full description of the Little Bow ASP project, please refer to the company’s website at www.zargon.ca.
  • After three years of preparation, Zargon is now ready to proceed with the construction phase of the Little Bow project. In particular, the Energy Resources Conservation Board (“ERCB”) regulatory scheme approval has been obtained, detailed engineering design has been completed, long lead time and large equipment orders have been placed and Class 3 construction cost estimates have been prepared. The project entails the construction of a water softening plant, chemical handling/mixing facilities and water injection facilities. In addition, there will be oil battery upgrades, pipeline replacements/upgrades, water injector conversions and well reactivations.
  • Including the $6.5 million of ASP costs spent in 2012, the total capital cost of the wholly owned phases 1 and 2 of the Little Bow ASP project is approximately $59 million (excluding the cost of capitalized chemicals). The scheduling of these expenditures is $38 million in 2013, $4 million in 2014, and $11 million in 2015 relating to the phase 2 implementation. With sanctioning, field construction will proceed during this summer, which will permit January 2014 first injection and initial incremental oil volumes by mid 2014.
  • Based on Southern Alberta analog pools and Little Bow reservoir model studies with predicted recoveries as high as a 17 percent incremental reservoir recovery, Zargon’s internal base case sanctioning economics use a 12 percent incremental reservoir recovery factor and predicts an estimated 4.87 million barrels of proved and probable oil reserves. The increased reserves are due in part to an updated reservoir model with increased chemical injections, and the corresponding phase 1 and 2 chemical costs for the six year chemical injection period (2014-2020) will be capitalized and are estimated at $66 million ($50 million PVBT 10%).
  • Based on Zargon’s base case economics, incremental oil production from phases 1 and 2 is estimated to average 1,470 barrels of oil per day in the five year 2016 to 2020 period. The long-life stable production profile of the ASP project is well suited for Zargon’s dividend paying business model.
  • Phase 1 and 2 field netbacks are estimated, assuming a field oil price of $68 per barrel ($85 Cdn. per barrel Edmonton par price), to be approximately $50 per barrel of incremental oil production. Zargon estimates that the phase 1 and 2 before tax rate of return for this enhanced oil recovery project will be 18 percent. The project is calculated to have a breakeven (PVBT 10%) field oil price of $48 per barrel. Potential upsides to these results could come from follow-on phases, higher oil prices, improved reservoir recoveries or Alberta Crown tertiary royalty modifications.
  • Follow-on capital expenditures for phases 3 and 4 of the Little Bow ASP project are expected to be completed by 2017 with forecasted total combined phase 1 to 4 peak production rates expected to occur in 2020 at a combined incremental production rate of 2,300 barrels of oil per day. For further information regarding the Little Bow ASP project, please refer to the company’s updated corporate presentation, which is available on our website at www.zargon.ca.

OPERATIONAL UPDATE:

  • Fourth quarter 2012 total production averaged 7,720 barrels of oil equivalent per day (on a 6:1 equivalency basis), a one percent increase from the prior quarter’s rate of 7,634 barrels of oil equivalent per day.
  • Fourth quarter 2012 oil and liquids production volumes averaged 5,065 barrels per day, essentially unchanged from 5,079 barrels per day in the prior quarter and less than one percent below production guidance levels of 5,100 barrels per day. On a production per million share basis (basic), oil and liquids production averaged 170 barrels per day in the fourth quarter essentially unchanged from the prior quarter’s rate of 171 barrels per day.
  • Fourth quarter 2012 natural gas production volumes averaged 15.93 million cubic feet per day, a four percent increase from the prior quarter rate of 15.33 million cubic feet per day and three percent above production guidance levels of 15.50 million cubic feet per day. The production gains came from the reactivation of natural gas wells that had been shut-in during the summer due to very low field natural gas prices.
  • Fourth quarter 2012 oil and liquids production represented 66 percent of total production based on a 6:1 equivalent basis, up from 61 and 58 percent weightings in fourth quarter 2011 and 2010, respectively.
  • For calendar 2012, Zargon’s production averaged 8,117 barrels of oil equivalent per day, comprised of 5,255 barrels of oil and liquids per day and 17.17 million cubic feet of natural gas per day.
  • During the full year 2012, Zargon spent $58.2 million (unaudited) on field activities and a further $6.5 million (unaudited) on the Little Bow ASP project. These expenditures were partially offset by a net $34.5 million (unaudited) of property dispositions and resulted in net 2012 total capital expenditures of $30.2 million (unaudited).
  • During the 2012 fourth quarter, Zargon spent $22.5 million (unaudited) on field capital programs (exclusive of $3.2 million of ASP related expenditures). Zargon completed an active 15.0 net well oil exploitation drilling program (13.0 net horizontal wells) that resulted in 14.0 net oil wells and 1.0 water disposal well. The drilling program included 4.8 Williston Basin horizontal Frobisher and Midale oil wells, 3.0 oil wells in the Taber Sunburst property, along with 4.0 Hamilton Lake and 2.0 Bellshill Lake oil exploitation wells in the Alberta Plains North core area. The capital program also included significant battery, pipeline and infrastructure upgrade expenditures at Hamilton Lake, Bellshill Lake, Little Bow, Elswick and Steelman.
  • Results from the Bellshill Lake and Taber fourth quarter drilling programs met or exceeded expectations. In the Williston Basin, three of the five locations met or exceeded expectations. At Hamilton Lake, three monobore horizontal multi-frac locations were drilled in an attempt to reduce costs and improve recoveries from our wholly owned 47 section Viking oil resource opportunity. Significant improvements in costs were made, but initial production data from these wells did not perform up to our 60 thousand barrels of oil reserves per well type curve that had been based on the results of the first five horizontal locations drilled on the property. Prior to drilling further wells on this property, we will rework our technical analysis to determine the optimal approach to develop the Hamilton Lake oil resource.
  • During this 2013 year’s “heavy spend” period for the construction of the Little Bow ASP project, Zargon will proceed with a modest conventional oil exploitation capital program. In the first quarter of 2013, we will drill five Midale drainage locations in the Williston Basin. In the summer, five Taber Sunburst and two Bellshill Viking horizontal wells are planned. Williston Basin drilling activities will resume this fall with an additional five locations. Additional wells will be added to the conventional oil exploitation budget throughout the year, as we complete the Little Bow construction project milestones.

2013 CAPITAL AND PRODUCTION GUIDANCE:

  • Zargon’s 2013 capital budget has been set at $40 million for (non-ASP) conventional projects with the drilling of 20 net oil exploitation wells, plus an additional $38 million for the Little Bow ASP project. This $78 million capital program is forecast to be funded by cash flows, bank debt and the sale of $20 million of minor non-strategic oil properties that are not related to Zargon’s six core conventional oil projects.
  • As at the end of the 2012 fourth quarter, Zargon’s debt net of working capital is $113.2 million (unaudited), a level that represents 51 percent of the $222.5 million of credit through convertible debentures and syndicated loan facilities.
  • With the revised (non-ASP) 2013 capital budget of $40 million, Zargon’s 2013 oil and liquids production guidance level has been revised to 5,000 barrels per day. This guidance is based on a 21 percent annual corporate oil and liquids production decline, the fourth quarter 2012 oil and liquids production rate of 5,065 barrels of oil per day and (non-ASP) capital program production addition efficiencies of $40,000 per barrel of oil and liquids per day. These guidance levels will be adjusted for acquisitions or dispositions as they occur. In the 2013 first quarter, oil and liquids production is forecast to average 5,150 barrels of oil per day.
  • Zargon’s 2013 natural gas production guidance is expected to average 15.0 million cubic feet per day, a production level that reflects a 12 percent “blowdown” corporate decline from 2012 exit rate production levels of 16.0 million cubic feet per day. In the 2013 first quarter, natural gas production is forecast to average 15.6 million cubic feet per day.
  • For 2013, Zargon has entered into 2,875 barrels of oil per day of oil fixed price sales contracts at an average price of $97.94 US per barrel, which represents 57.5 percent of the 2013 production guidance levels.

2012 YEAR END RESERVES:

  • Zargon’s 2012 year end proved and probable total reserves decreased nine percent to 31.19 million barrels of oil equivalent. These reserves were appraised by Zargon’s independent reserves evaluator McDaniel & Associates Consultants Ltd. (“McDaniel”) and are effective as of December 31, 2012. On a 6:1 equivalency basis, oil and liquids comprised 74 percent of Zargon’s total proved and probable reserves at year end 2012, up from a 70 percent weighting at the end of 2011.
  • Zargon’s 2012 year end proved and probable oil and liquids reserves decreased four percent to total 23.05 million barrels. On a per share basis (basic), Zargon’s 2012 year end proved and probable oil and liquids reserves were 0.77 barrels, a six percent decrease over the prior year. The proved and probable oil and liquids reserves estimate includes 4.39 million barrels of probable undeveloped oil equivalent reserves assigned using a 10 percent incremental reservoir recovery factor to the ASP tertiary oil recovery project at Little Bow, Alberta.
  • Zargon’s 2012 year end proved and probable natural gas reserves decreased 21 percent to total 48.82 billion cubic feet, due to a combination of production and 7.02 billion cubic feet of negative reserve adjustments relating to economic factors. Zargon’s business is completely focused on oil exploitation, and Zargon has not drilled a gas well since the fall of 2010. Over 90 percent of Zargon’s proved and probable discounted cash flows (PVBT 10%) are attributable to oil and liquids production.
  • Zargon’s oil properties are characterized by pressure supported reservoirs (waterflood or natural aquifers) that provide long-life, low-decline oil production. Consequently, Zargon’s proved developed producing oil and liquids reserve life index is 6.9 years and Zargon’s proved and probable producing oil and liquids reserve life index is 9.3 years. These low decline oil reserves are well suited for Zargon’s dividend paying business model.
  • Zargon’s year end 2012 “produce-out” net asset value is calculated to be $12.79 per basic share. This estimate reflects McDaniel’s estimate of the Zargon properties’ proved and probable future cash flow using a before tax 10 percent discount rate and forecast prices and costs plus an independent appraisal of Zargon’s undeveloped land less an allowance for the year end bank debt, the full future face value of the $57.5 million convertible debenture and working capital deficiencies. On a proved and probable developed producing reserve assignment basis, Zargon’s “produce-out” net asset value is calculated to be $10.64 per basic share. The corresponding proved developed producing net asset value estimate is $7.75 per basic share.

DETAILED RESERVE INFORMATION:

Reserves included herein are stated on a gross company working interest basis unless otherwise noted. All reserves information has been prepared in accordance with National Instrument 51-101 Standards of Disclosure (“NI 51-101”). In addition to the detailed information disclosed in this press release, more detailed information will be included in Zargon’s 2012 Annual Information Form to be filed on SEDAR (www.sedar.com) and posted on our website (www.zargon.ca) in March 2013.

Based on the independent reserves evaluation conducted by McDaniel effective December 31, 2012, and prepared in accordance with NI 51-101, Zargon had proved and probable reserves of 31.19 million barrels of oil equivalent. Reserve reductions from exploration and development activities (including revisions) and corporate and net property acquisitions/dispositions were negative 0.13 million barrels of oil equivalent.

Company Reserves(1)
At December 31, 2012 Oil and Liquids
(mmbbl
) Natural Gas
(bcf
) Equivalents (2)
(mmboe
)
Proved producing 12.74 26.61 17.18
Proved non-producing 0.44 3.23 0.98
Proved undeveloped 0.23 0.08 0.24
Total proved 13.41 29.92 18.40
Probable additional producing 4.56 9.14 6.08
Probable non-producing and undeveloped 5.08 9.76 6.71
Total probable additional 9.64 18.90 12.79
Total proved and probable producing 17.30 35.75 23.26
Total proved and probable 23.05 48.82 31.19
Proved producing reserve life index, years (3) 6.9 4.6 6.1
Proved reserve life index, years (3) 7.2 5.1 6.5
Proved and probable producing reserve life index, years (3) 9.3 6.1 8.2
Proved and probable reserve life index, years (3) 12.4 8.4 11.0
1. Company working interest reserves are gross reserves before deduction of royalties, boe (6:1).
2. Boes may be misleading, particularly if used in isolation. A boe conversion ratio of 6 mcf:1 bbl is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead.
3. Reserve life is calculated using annualized fourth quarter 2012 production.

A summary reconciliation of the 2012 year end reserve assignments with the reserves reported in the 2011 year end report based on McDaniel’s forecast prices and costs is presented below:

Reserve Reconciliation (All Categories)
Oil and Liquids (mmbbl ) Natural Gas (bcf ) Equivalents (mmboe )
Proved Probable Proved
& Prob.
Proved Probable Proved
& Prob.
Proved Probable Proved
& Prob.
December 31, 2011 14.60 9.45 24.05 39.37 22.06 61.43 21.16 13.13 34.29
Discoveries and extensions 0.97 0.45 1.42 0.43 0.18 0.61 1.05 0.48 1.53
Revisions 0.57 0.03 0.60 (3.66 ) (3.36 ) (7.02 ) (0.04 ) (0.53 ) (0.57 )
Acquisitions and dispositions (0.81 ) (0.29 ) (1.10 ) 0.06 0.02 0.08 (0.80 ) (0.29 ) (1.09 )
Production (1.92 ) (1.92 ) (6.28 ) (6.28 ) (2.97 ) (2.97 )
December 31, 2012 13.41 9.64 23.05 29.92 18.90 48.82 18.40 12.79 31.19

On a proved and probable basis, Zargon’s oil and liquids reserves from development activities increased by 2.02 million barrels, and after net dispositions of 1.10 million barrels the net increase was 0.92 million barrels before production of 1.92 million barrels. Overall, field capital exploration and development programs provided 1.53 million barrels of oil equivalent of new additions. Net property acquisitions/dispositions for 2012 removed 1.09 million barrels of oil equivalent, and provided $34.5 million of net proceeds to Zargon. During the year, positive technical revisions pertaining to Alberta Plains Taber and Little Bow and the Williston Basin Elswick and Ralph oil exploitation properties were partially offset by negative oil reserve adjustments at Alberta Plains North St. Anne property and other minor properties. With the sharply lower natural gas prices in 2012, negative proved and probable natural gas revisions totaling 7.02 billion cubic feet were booked at Jarrow, Pembina and other selected Alberta properties. As a result, overall technical reserve revisions were a negative 0.57 million barrels of oil equivalent.

Reserve Reconciliation (Developed Producing)
Oil and Liquids (mmbbl ) Natural Gas (bcf ) Equivalents (mmboe )
Proved Probable Proved
& Prob.
Proved Probable Proved
& Prob.
Proved Probable Proved
& Prob.
December 31, 2011 13.69 4.71 18.40 33.71 11.53 45.24 19.31 6.63 25.94
Discoveries and extensions 0.92 0.37 1.29 0.43 0.19 0.62 0.99 0.40 1.39
Revisions 0.86 (0.26 ) 0.60 (1.31 ) (2.60 ) (3.91 ) 0.65 (0.70 ) (0.05 )
Acquisitions and dispositions (0.81 ) (0.25 ) (1.06 ) 0.06 0.02 0.08 (0.80 ) (0.25 ) (1.05 )
Production (1.92 ) (1.92 ) (6.28 ) (6.28 ) (2.97 ) (2.97 )
December 31, 2012 12.74 4.57 17.31 26.61 9.14 35.75 17.18 6.08 23.26

Zargon’s reserves are characterized by a high developed producing component. Proved developed producing reserves represent 93 percent of total proved reserves while proved and probable developed reserves account for 75 percent of total proved and probable reserves. For the Little Bow ASP project, McDaniel has assigned 4.39 million barrels of oil equivalent reserves in the probable undeveloped category, which represents 83 percent of the undeveloped reserves and 14 percent of Zargon’s total proved and probable reserves assignment.

FINDING, DEVELOPMENT AND ACQUISITION COSTS:

We have presented finding and development costs below both including and excluding acquisitions and dispositions. While NI 51-101 requires that the effects of acquisitions and dispositions be excluded, we have included these items because we believe that acquisitions and dispositions can have a significant impact on our ongoing reserve replacement costs and that excluding these amounts could result in an inaccurate portrayal of our cost structure.

For 2012, Zargon’s proved and probable finding, development and acquisition (“FD&A”) costs, taking into account reserve revisions and changes in estimated future development capital during the period were not meaningful due to net dispositions and natural gas reserve write downs. For the purposes of this calculation, the $30.2 million of 2012 net capital additions was combined with a decrease in estimated future development capital for proved and probable reserves of $5.3 million ($123.5 million at December 31, 2012 compared to $128.8 million at December 31, 2011). More than 80 percent of Zargon’s 2012 year end future capital costs are attributed to the Little Bow ASP project.

Excluding acquisitions (and dispositions), Zargon’s 2012 proved and probable finding and development (“F&D”) costs were $61.82 per barrel of oil equivalent. Considering that essentially all of Zargon’s 2012 capital program was directed to oil projects, it is insightful to calculate Zargon’s proved and probable F&D costs on an “oil only” basis ($58.2 million of conventional capital expenditures plus $6.5 million of ASP capital expenditures, less a $5.3 million change in future capital estimates with 2.02 million barrels of oil and liquid additions). Using this approach, proved and probable F&D “oil only” costs were $29.38 per barrel.

Similarly, Zargon’s proved and probable FD&A costs on an “oil only” basis were $27.01 per barrel ($58.2 million of conventional capital expenditures plus $6.5 million of ASP capital expenditures, less $34.5 million of net dispositions and less a $5.3 million change in future capital estimates with 0.92 million barrels of oil and liquid additions). These “oil only’ costs compare with Zargon’s unaudited 2012 corporate average field oil netback (before interest, general and administrative and other costs) of more than $40 per barrel of oil (unaudited).

Proved and Probable Finding, Development and Acquisition Costs (1)
2012 2011 2010(4)
Total net capital expenditures ($ millions) – unaudited (2) 30.19 48.29 71.38
Total net capital expenditures plus change in forecast future development costs ($ millions) (2) 24.85 144.52 79.62
Proved and probable reserves (mmboe)
Open 34.29 32.39 32.24
Discoveries and extensions 1.53 5.77 3.07
Acquisitions and dispositions (1.09 ) 0.06 1.53
Revisions (0.57 ) (0.59 ) (0.84 )
Production (2.97 ) (3.34 ) (3.61 )
Close 31.19 34.29 32.39
Proved and probable FD&A costs ($/boe) (3) 27.58 21.18
Proved and probable three-year FD&A costs ($/boe) (3) 28.07 21.48 18.83
Proved and probable F&D costs ($/boe) (3) 61.82 32.41 30.79
Proved and probable three-year F&D costs ($/boe) (3) 35.35 30.06 24.80
1. The aggregate of the exploration and development costs incurred in the most recent financial year and the change during that year in estimated future development costs generally will not reflect total finding and development costs related to reserves additions for that year.
2. Amounts exclude additions for administrative assets.
3. Amounts are calculated including the change in future development costs.
4. 2010 numbers do not reflect any changes to accounting rules which may have occurred.

NET ASSET VALUE:

Zargon’s oil, liquids and natural gas reserves were evaluated using McDaniel’s price forecasts effective January 1, 2013, prior to provisions for income taxes, interest, debt service charges, transaction costs and general and administrative expenses. The estimated values of future net revenue disclosed do not represent the fair market value of the reserves.

Before Tax Present Value of Future Net Revenue
(Forecast Prices and Costs)
Discount Factor
($ millions) 0% 5% 10% 15%
Proved producing 491.3 388.8 323.0 278.1
Proved non-producing 14.7 12.2 10.3 8.7
Proved undeveloped 7.9 5.9 4.5 3.5
Total proved 513.9 406.9 337.8 290.3
Probable additional producing 225.9 130.0 86.2 62.6
Probable additional non-producing and undeveloped 157.8 90.1 49.5 23.6
Total probable additional 383.7 220.1 135.7 86.2
Total proved and probable producing 717.2 518.8 409.2 340.7
Total proved and probable 897.6 627.0 473.5 376.5

The following net asset value table shows what is customarily referred to as a “produce-out” net asset value calculation under which the current value of Zargon’s reserves would be produced at McDaniel’s forecast future prices and costs. The value is a snapshot in time as at December 31, 2012, and is based on various assumptions including commodity prices and foreign exchange rates that vary over time. In this analysis, the present value of the proved and probable reserves is calculated at a before tax 10 percent discount rate. In the net asset value calculation, Zargon’s 337 thousand net acres of land is valued at $21.7 million based on the independent firm of Seaton-Jordan & Associates Ltd. valuation as at December 31, 2012.

Net Asset Value
As at December 31 ($ millions) 2012
Proved and probable reserves (PVBT 10%) (1) 473.5
Undeveloped land 21.7
Working capital (excluding unrealized derivative assets/ liabilities) – unaudited (19.9 )
Bank debt – unaudited (35.7 )
Convertible debenture – unaudited (57.5 )
Net asset value 382.1
Net asset value per share ($/basic share) (2) 12.79
1. McDaniel’s estimate of future before tax cash flow discounted at PV 10 percent.
2. Calculated using basic total shares outstanding at December 31, 2012 of 29.868 million shares.

The following table provides net asset value estimates at December 31, 2012 for all four reserve categories.

Reserves Category McDaniel PVBT 10%
($ million)
(1
) Net Asset Value
($ million)
(2
) Net Asset Value
($/basic share)
(3
)
Proved, developed, producing reserves 323.0 231.6 7.75
Total proved reserves 337.8 246.3 8.25
Proved and probable, developed producing reserves 409.2 317.8 10.64
Proved and probable reserves 473.5 382.1 12.79
1. McDaniel’s estimate of future before tax cash flow discounted at PV 10 percent.
2. McDaniel’s estimated value, adjusted for the following unaudited items at December 31, 2012:
– Undeveloped land value as assessed by Seaton Jordan of $21.7 million; and
– Net debt of $113.2 million, which includes full value of the convertible debenture of $57.5 million.
3. Calculating using basic total shares outstanding at December 31, 2012 of 29.868 million shares.

Forward-Looking Statements – This press release contains forward-looking statements relating to our plans and operations as at February 20, 2013. Forward-looking statements typically use words such as “anticipate”, “continue”, “estimate”, “expect”, “forecast”, “may”, “will”, “project”, “should”, “plan”, “intend”, “believe” and similar expressions (including the negatives thereof). In particular, this press release contains forward-looking statements relating, but not limited to: our business strategy, plans and management focus; the timing of release of our 2012 financial results, our 2013 and beyond capital expenditure program, the source of funding of our 2013 and beyond capital program, anticipated 2013 and beyond production guidance and product mix, drilling, completion, development and exploitation plans and the results therefrom, future drilling locations, plans to sell non-strategic assets and to review and implement cost saving opportunities, plans with respect to our Little Bow ASP project, anticipated netbacks, capital expenditures and other costs associated with the ASP project and the anticipated results from this project, and sources of funding for our capital expenditure program. In addition, all statements relating to reserves in this press release are deemed to be forward-looking as they involve an implied assessment, based on certain assumptions and estimates, that the reserves described, can be properly produced in the future.

By their nature, forward-looking statements are subject to numerous risks and uncertainties, some of which are beyond our control, such as those relating to results of operations and financial condition, general economic conditions, industry conditions, changes in regulatory and taxation regimes, volatility of commodity prices, escalation of operating and capital costs, currency fluctuations, the availability of services, imprecision of reserve estimates, geological, technical, drilling and processing problems, environmental risks, weather, the lack of availability of qualified personnel or management, stock market volatility, the ability to access sufficient capital from internal and external sources and competition from other industry participants for, among other things, capital, services, acquisitions of reserves, undeveloped lands and skilled personnel. Risks are described in more detail in our Annual Information Form, which will be available on sedar and our website. Forward-looking statements are provided to allow investors to have a greater understanding of our business.

You are cautioned that the assumptions, including, among other things, future oil and natural gas prices; future capital expenditure levels; future production levels; future exchange rates; the cost of developing and expanding our assets; our ability to obtain equipment in a timely manner to carry out development activities; our ability to market our oil and natural gas successfully to current and new customers; the impact of increasing competition; our ability to obtain financing on acceptable terms; and our ability to add production and reserves through our development and acquisition activities used in the preparation of such information, although considered reasonable at the time of preparation, may prove to be imprecise and, as such, undue reliance should not be placed on forward-looking statements. Our actual results, performance, or achievement could differ materially from those expressed in, or implied by, these forward-looking statements. We can give no assurance that any of the events anticipated will transpire or occur or, if any of them do, what benefits we will derive from them. The forward-looking information contained in this document is expressly qualified by this cautionary statement. Our policy for updating forward-looking statements is that Zargon disclaims, except as required by law, any intention or obligation to update or revise any forward-looking statements, whether as a result of new information, future events or otherwise.

Other Advisories – Boe’s may be misleading, particularly if used in isolation. A boe conversion ratio of 6 Mcf: 1 bbl is based on an energy equivalency conversion method primarily applicable at the burner tip and does not represent a value equivalency at the wellhead. In addition, given that the value ratio based on the current price of crude oil as compared to natural gas is significantly different from the energy equivalency of 6:1, utilizing a conversion ratio on a 6:1 basis may be misleading as an indication of value. The estimates of reserves and future net revenue for individual properties may not reflect the same confidence level as estimates of reserves and future net revenue for all properties, due to the effects of aggregation.

FURTHER INFORMATION:

Zargon Oil & Gas Ltd. is a Calgary based oil and natural gas company working in the Western Canadian and Williston sedimentary basins that has delivered a long history of returns and dividends (distributions). Zargon’s business is focused on oil exploitation projects that profitably increase oil production and recovery factors from existing oil reservoirs.

In order to learn more about Zargon, we encourage you to visit Zargon’s website at www.zargon.ca where you will find a current shareholder presentation, financial reports and historical news releases.

Contact:

C.H. Hansen
President and Chief Executive Officer
403-264-9992

J.B. Dranchuk
Vice President, Finance and Chief Financial Officer
403-264-9992

Zargon Oil & Gas Ltd.
zargon@zargon.ca
www.zargon.ca

Sign up for the BOE Report Daily Digest E-mail Return to Home