The operator of Canada’s Trans Mountain oil pipeline expects to launch a process by early January to gauge commercial interest in a capacity expansion by approximately 210,000 barrels per day, CEO Mark Maki said on Friday.
The process, known as an open season, would determine whether there is enough shipper interest to build Trans Mountain’s Mainline Optimization Project, which would involve constructing about 30 km (19 miles) of new pipe in British Columbia and adding 11 new pump stations along the existing pipeline.
Trans Mountain is targeting April 2027 for a final investment decision on the project, Maki said in an interview, with a construction completion date in late 2028.
The Trans Mountain pipeline, owned by the Canadian government, transports oil from Alberta to BC’s west coast, where it can be shipped to overseas markets including China.
Trans Mountain completed a C$34 billion ($24 billion) expansion in 2024, tripling the pipeline’s capacity to 890,000 bpd. Oil sands production in Canada continues to rise, however, and the Trans Mountain system has been running full this autumn.
Late last month, Trans Mountain’s operator completed a separate project that involved adding chemical additives to reduce pipeline friction, giving it the ability to increase capacity by up to 10%, or 90,000 bpd, depending on market demand.
In September, Canada’s federal government sent letters to 129 First Nations along the Trans Mountain pipeline route, offering them a combined 15% equity ownership stake in the pipeline.
The government has held four confidential information sessions with First Nations about the opportunity, Maki said, adding he expects any potential equity transaction would likely take place in late 2028, after the completion of the Mainline Optimization Project.
(Reporting by Amanda Stephenson in Calgary; Editing by Rod Nickel)