2020 capital expenditures cut ~50% from December 2019 guidance
Liquidity increased by $500 million to $5.2 billion
Integrated Corridor upstream production reduced by over 80,000 bbls/day / U.S. refinery throughput reduced
Protection of workers and communities remains top priority
CALGARY, Alberta – Husky Energy (TSX:HSE) is significantly reducing capital expenditures and shutting in negative cash margin production as further measures to strengthen its business given market conditions caused by COVID-19.
“We have taken immediate action to preserve our balance sheet and core business in this commodity price environment,” said CEO Rob Peabody. “Our focus remains on health and safety, and on increasing Husky’s resilience.
“As the market rebalances supply with demand over a very short period in North America, negative cash margins before operating costs are occurring. Reducing production minimizes our negative cash margin exposure.”
Husky has important advantages in the current economic environment, including: a strong balance sheet, an Integrated Corridor that includes a sizeable midstream and downstream segment, and Offshore operations underpinned by long-term gas contracts in the Asia Pacific region.
Husky’s plan includes:
- Continuing to advance process and occupational safety performance
- Reducing and deferring all discretionary capital spending
- Liquidity improvements
- Reducing production and refinery throughput to address near-term negative cash margins until supply and demand is rebalanced
Additional $700 Million in Capital Reductions
Husky previously announced 2020 spending reductions of $1 billion, including $900 million in capital expenditures and $100 million in cost-saving measures.
2020 capital guidance is further revised as follows:
New | March 12 ’20 Revision | Dec. ’19 Guidance | |
Capital Investment1 ($ millions) | |||
Upstream | 1,100 – 1,200 | 1,750 – 1,900 | 2,625 – 2,800 |
Downstream | 475 – 550 | 475 – 550 | 475 – 550 |
Total | 1,600 – 1,800 | 2,300 – 2,500 | 3,200 – 3,400 |
1Includes exploration capital and other capital expenditures but excludes asset retirement obligations, capitalized interest and Superior Refinery rebuild capital. |
Planned 2020 Capital Expenditures By Quarter ($ millions) | |||
Q1 | Q2 | Q3 | Q4 |
600 – 630 | 350 – 400 | 400 – 450 | 270 – 320 |
Production and Throughput Reductions
Husky continues to safely shut-in production across its Integrated Corridor business, where appropriate. To date, Integrated Corridor production has been reduced by more than 80,000 barrels per day (bbls/day), most of which is heavy oil, with the ability to reduce even further while preserving the option to quickly ramp back up should pricing conditions allow.
Integrated Corridor production is being aligned with upgrading and refining requirements as throughput is adjusted and optimized in line with changing market conditions. As a result, updated 2020 production and throughput guidance will not be provided at this time. Current U.S. refinery throughput has been reduced by around 95,000 bbls/day, or approximately 40% below maximum capacity.
INCREASED LIQUIDITY
Husky continues to prioritize its balance sheet, supported by significant liquidity. As of the end of the first quarter, the Company had approximately $4.7 billion of liquidity, comprised of $1.3 billion in cash and $3.4 billion in available credit facilities.
Since the end of the first quarter, Husky has increased its liquidity with the recent addition of a $500 million term loan, increasing total liquidity towards $5.2 billion. The term loan proceeds have been used to repay syndicate drawings advanced to repay the maturing 5.0% notes on March 12, 2020.
The Company has no long-term debt maturities until 2022.
OPERATIONS AND PROJECT UPDATES
Husky Lloydminster Upgrader
A planned turnaround scheduled to begin in April 2020 has been deferred to late Q3 2020, given the current safety and public health risks inherent in mobilizing and maintaining a large construction workforce during the COVID-19 pandemic. Maintenance work at the Upgrader will proceed where necessary and safe to do so, and operations and throughput will be modified in accordance with maintenance requirements.
A project at the Upgrader to increase diesel production from 6,000 bbls/day to nearly 10,000 bbls/day has also been deferred to late Q3 2020.
Superior Refinery
Rebuild construction at the Superior Refinery in Wisconsin has been suspended due to the safety and public health risks inherent in maintaining a large construction workforce during the COVID-19 pandemic. A schedule for resumption will be determined in due course. Rebuild costs are expected to be substantially covered by property damage insurance.
Lloydminster Thermal Projects
Lloydminster thermal bitumen production, including the Tucker Thermal Project, has been reduced due to anticipated production backlogs in Western Canada as North American refinery throughputs adjust to the dramatic stall in product consumption.
These types of projects have the flexibility to be safely ramped down to minimum rates and then quickly ramped back up once pricing conditions improve.
Commissioning activities are being completed at the 10,000-barrel-per-day Spruce Lake Central thermal project, with enhanced health and safety protocols in place. Startup will be dependent on improved pricing conditions.
Construction of the 10,000 barrel-per-day Spruce Lake North thermal project, originally scheduled for completion around the end of 2020, has been suspended, and additional Lloyd projects to be delivered beyond 2020 have been deferred.
Sunrise Energy Project
A major turnaround that was scheduled to start at Sunrise in April has been deferred due to public health and safety considerations related to COVID-19. Other maintenance work at Sunrise will proceed where necessary and safe to do so, with operations and production modified in accordance with maintenance requirements.
Husky operates Sunrise and its partner operates the jointly-owned BP-Husky Toledo Refinery near Toledo, Ohio.
Western Canada Production
Western Canada oil and gas production is being reduced or shut in. No further capital expenditures are planned in 2020.
Atlantic Region
Major construction activities related to the West White Rose Project have been suspended due to COVID-19.
Production at the main White Rose field continues, with enhanced workforce control measures designed to ensure safe operations on the SeaRose floating production, storage and offloading (FPSO) vessel. Husky has a 72.5% working interest in the White Rose field and a 68.8% working interest in the satellite extensions, including West White Rose.
The planned drydock for the Terra Nova FPSO vessel is being reviewed by the operator and alternative options are being considered to complete maintenance work and asset-life extension activities. Husky has a 13% working interest in the Terra Nova oil field.
Asia Pacific Region
Production at the Liwan Gas Project offshore China has returned to full rates following an extended Chinese New Year break related to the COVID-19 pandemic. Husky has a 49% working interest in the Liwan 3-1 and Liuhua 34-2 fields.
The Liuhua 29-1 field at Liwan is advancing towards first production by the end of 2020. Husky holds a 75% working interest in the field, which once fully ramped up will add approximately 9,000 barrels of oil equivalent per day to its fixed-price Asia Pacific production.
The BD Project in the Madura Strait offshore Indonesia has returned to full rates following planned maintenance in the first quarter. Husky has a 40% working interest in the project.
Canadian Retail & Commercial Fuels Business
Due to the current market environment, Husky has suspended the strategic review of its Canadian retail and commercial fuels business, which consists of more than 500 stations, travel centres, cardlock operations and bulk distribution facilities.