TC Energy said on Monday it plans to develop the Alberta Growth Connector, a proposed 370-kilometre natural gas pipeline that would connect Western Canadian supply with Alberta’s oil sands region, as it aims to meet accelerating demand in the province.
Reuters had reported earlier this month that the Canadian energy company was preparing to unveil a “meaningful” expansion plan for its NGTL natural gas pipeline system to address Alberta’s concerns about constrained capacity.
* The 48-inch pipeline would initially add about 1 billion cubic feet per day (bcf/d) of capacity to the company’s existing NGTL network, with potential for expansion as demand grows
* The company expects total demand on its NGTL system to rise about 25% to roughly 18 bcf/d by 2031, from 14.4 bcf/d in 2026
* The 2031 projection is about 1.5 bcf/d higher than the outlook presented in last year’s annual plan, with more than 60% of the forecast increase expected to come from Alberta’s oil sands, power generation and data center sectors
* The Alberta Growth Connector remains subject to customer commitments, stakeholder engagement, regulatory approvals and TC Energy’s internal sanctioning process
* TC Energy’s NGTL system currently moves an average of 15 billion cubic feet of natural gas per day, gathering it from producers across the province and connecting it to markets, storage facilities and export connections across Canada and the United States
* The company is also advancing about C$1.2 billion ($840.69 million) of sanctioned NGTL expansion projects
(Reporting by Dharna Bafna in Bengaluru; Editing by Shilpi Majumdar)