• Sign up for the Daily Digest E-mail
  • X
  • LinkedIn
  • See more results

    Generic selectors
    Exact matches only
    Search in title
    Search in content
    Post Type Selectors

BOE Report

Sign up

See more results

Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
  • Home
  • StackDX Intel
  • Headlines
    • Latest Headlines
    • Featured Companies
    • Columns
    • Discussions
  • Well Activity
    • Well Licences
    • Well Activity Map
  • Property Listings
  • Land Sales
  • M&A Activity
    • M&A Database
    • AER Transfers
  • Markets
  • Rig Counts/Data
    • CAOEC Rig Count
    • Baker Hughes Rig Count
    • USA Rig Count
    • Data
      • Canada Oil Market Data
      • Canada NG Market Data
      • USA Market Data
      • Data Downloads
  • Jobs

North West Upgrading’s Sturgeon refinery costs levelling at $8.5 billion

October 8, 20152:00 AM The Canadian Press0 Comments

CALGARY – The costs of building Alberta’s first new oil refinery in 30 years have stabilized and it’s on track to be up and running by 2017, says the chairman of the company developing the government-backed Sturgeon project.

Ian MacGregor, chairman and chief executive of North West Upgrading Inc., says that with close to $5 billion already spent, he expects the total cost of constructing the refinery to come within the company’s $8.5 billion estimate.

That’s in line with what the company has been saying since late 2013, when it hiked the projected cost by 50 per cent — from $5.7 billion — and said the refinery wouldn’t be ready for a 2016 start-up.

In early planning stages, the project was estimated to cost less than $4 billion and some critics have referred to the swelling costs of the refinery as a boondoggle.

But North West Upgrading, which has partnered with Canadian Natural Resources Ltd. to develop the refinery, hasn’t encountered any new problems that could push the cost beyond the current $8.5 billion estimate, MacGregor says.

“It’s the first time in the last 10 years I can say that,” he said at a briefing this week. “I think we’re on the right side of that.”

Once completed, the refinery will be able to process 50,000 barrels of bitumen a day and refine it into low-sulphur diesel fuel. The company has plans to add two more phases with the same capacity in the future.

The Alberta government has committed to supplying three-quarters of the oil that will be processed thanks to a program in which it takes barrels of bitumen as delivery instead of royalty payments.

Last year, the government estimated it would have to pay $26 billion in tolls over 30 years to process that bitumen through the refinery, up from an earlier estimate of $19 billion.

Ted Morton, a former provincial finance and energy minister and current professor at University of Calgary’s School of Public Policy, has called the project a “multibillion-dollar boondoggle with high risks for Alberta taxpayers.”

Morton estimates the government will have to pay $63 a barrel in processing costs, but MacGregor disagrees, saying the cost will actually be about $35 a barrel.

Energy Minister Margaret McCuaig-Boyd said in a statement that the Sturgeon refinery is an initiative of the previous government, but that the NDP is looking at ways to create more value-added products in the province.

“We are considering our options when it comes to the best options for upgrading and refining. Specifically, the royalty review panel is considering ways to encourage and benefit from upgrading and refining as a part of its work.”

The Sturgeon project, located about 45 kilometres northeast of Edmonton, is also incorporating a carbon-capturing element, where about two-thirds of the refinery’s carbon dioxide will be captured and then used to recover more oil from depleted wells in the province.

MacGregor said that the diesel produced from the refinery will have five to 10 per cent fewer emissions compared with conventional U.S. oil production, whereas average oilsands production is 20 per cent worse than conventional American oil today.

More processing alongside a smaller environmental footprint are critical for Alberta’s economy, he said.

“If we’re thinking what’s going to protect the economy, I believe it’s refining and carbon capture, and if we don’t do those things, forget it, we’re going to be rolling up the sidewalks,” he said.

Follow @ibickis on Twitter

Canadian Natural Resources

Follow BOE Report
  • Facebook
  • X
  • LinkedIn

Sign up for the BOE Report Daily Digest E-mail

Successfully subscribed

Latest Headlines
  • Saudi Arabia says it destroyed drones launched by Iran-backed groups in Iraq
  • Crude oil futures are pricing market adaptability, not hopeful Iran peace: Russell
  • Expand Energy to beef up gas marketing business with $1.25 billion Twin Eagle deal
  • Saturn Oil & Gas Inc. Announces Completion of the Offer for the Common Shares of Burgess Creek Exploration Inc. and Mandatory Extension Period to August 6, 2026
  • Ukraine’s attacks on Russian energy sites — what has been hit?

Return to Home
Alberta GasMonthly Avg.
CAD/GJ
Market Data by TradingView

    Report Error







    Note: The page you are currently on will be sent with your report. If this report is about a different page, please specify.

    About
    • About BOEReport.com
    • In the News
    • Terms of Use
    • Privacy Policy
    • Editorial Policy
    Resources
    • Widgets
    • Notifications
    • Daily Digest E-mail
    Get In Touch
    • Advertise
    • Post a Job
    • Contact
    • Report Error
    StackDX
    • BOE Report Jobs
    • StackDX Intel
    © 2026 Stack Technologies Ltd.