• Sign up for the Daily Digest E-mail
  • X
  • LinkedIn
  • See more results

    Generic selectors
    Exact matches only
    Search in title
    Search in content
    Post Type Selectors

BOE Report

Sign up

See more results

Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
  • Home
  • StackDX Intel
  • Headlines
    • Latest Headlines
    • Featured Companies
    • Columns
    • Discussions
  • Well Activity
    • Well Licences
    • Well Activity Map
  • Property Listings
  • Land Sales
  • M&A Activity
    • M&A Database
    • AER Transfers
  • Markets
  • Rig Counts/Data
    • CAOEC Rig Count
    • Baker Hughes Rig Count
    • USA Rig Count
    • Data
      • Canada Oil Market Data
      • Canada NG Market Data
      • USA Market Data
      • Data Downloads
  • Jobs

NEB restores orders and decisions issued to Trans Mountain prior to court ruling

July 19, 20193:55 PM The Canadian Press0 Comments

Trans Mountain pipeline

CALGARY – The National Energy Board says its decisions and orders regarding the Trans Mountain pipeline expansion issued prior to last summer when a court overturned its approval will remain valid except where circumstances have changed.

The decision is in line with a request from the federal government-owned pipeline to restore its regulatory status in order for construction to resume during this building season.

Trans Mountain says it is reviewing the details of Friday’s decision and will decide on processes and a construction schedule in the coming weeks.

The NEB, which invited comment on the issue from June 21 to July 9, says it may review any of its decisions or orders on its own, due to new information from Trans Mountain or in response to an application for review.

It says Trans Mountain must issue notices to landowners along the entire route, including those that were served previously, and publish notices in local newspapers.

The NEB says it will notify potentially affected Indigenous peoples of the detailed route approval process, adding those who have route concerns may file a statement of opposition requesting a review.

Before the Federal Court of Appeal decision last August, the NEB had approved more than 73 per cent of the detailed route and found that 64 of 98 pre-construction conditions had been fully satisfied, allowing Trans Mountain to start construction at the Westridge Marine Terminal and on certain temporary infrastructure sites and portions of the pipeline route.

The NEB reapproved the project in February after considering impacts on marine life and Ottawa gave final approval June 18 after completing consultations with Indigenous groups.

Follow BOE Report
  • Facebook
  • X
  • LinkedIn

Sign up for the BOE Report Daily Digest E-mail

Successfully subscribed

Latest Headlines
  • Tenaz Energy Corp. Announces Q1 2026 Results
  • Enbridge Inc. Announces Election of Directors
  • Athabasca Oil Reports Strong 2026 First Quarter Results and Increased Cash Flow Outlook
  • Cenovus reports voting results of annual meeting of shareholders
  • Petrus Resources Announces First Quarter 2026 Financial and Operating Results

Return to Home
Alberta GasMonthly Avg.
CAD/GJ
Market Data by TradingView

    Report Error







    Note: The page you are currently on will be sent with your report. If this report is about a different page, please specify.

    About
    • About BOEReport.com
    • In the News
    • Terms of Use
    • Privacy Policy
    • Editorial Policy
    Resources
    • Widgets
    • Notifications
    • Daily Digest E-mail
    Get In Touch
    • Advertise
    • Post a Job
    • Contact
    • Report Error
    BOE Network
    © 2026 Stack Technologies Ltd.