CALGARY – Trans Mountain Corp. says a project to increase the amount of crude that can flow on its Alberta-to-B.C. pipeline using chemical additives has been completed two months ahead of schedule.
The drag-reducing agent increases the pipeline’s capacity by about 10 per cent to 980,000 barrels per day.
A further expansion of 210,000 barrels per day, using new pipeline segments and pump stations, is expected to come into service by the end of 2028.
During the third quarter, the Crown corporation says its pipeline shipped 840,000 barrels per day on average, up from 777,000 barrels during the same three months of 2025.
Net income for the quarter rose to $132 million from $127 million as revenues increased to $825 million from $765 million.
So far this year, Trans Mountain has paid $1.45 billion to its owner, the federal government, in interest payments, dividends and return of capital distributions.
This report by The Canadian Press was first published Nov. 27, 2026.