• Sign up for the Daily Digest E-mail
  • X
  • LinkedIn
  • See more results

    Generic selectors
    Exact matches only
    Search in title
    Search in content
    Post Type Selectors

BOE Report

Sign up

See more results

Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
  • Home
  • StackDX Intel
  • Headlines
    • Latest Headlines
    • Featured Companies
    • Columns
    • Discussions
  • Well Activity
    • Well Licences
    • Well Activity Map
  • Property Listings
  • Land Sales
  • M&A Activity
    • M&A Database
    • AER Transfers
  • Markets
  • Rig Counts/Data
    • CAOEC Rig Count
    • Baker Hughes Rig Count
    • USA Rig Count
    • Data
      • Canada Oil Market Data
      • Canada NG Market Data
      • USA Market Data
      • Data Downloads
  • Jobs

Court hearings to begin this week into Enbridge cross-border oil pipelines

September 7, 20157:01 AM The Canadian Press

CALGARY – A U.S. court begins hearing arguments this week in a lawsuit that claims increased volumes of oilsands crude have been allowed to flow from Canada into the United States without adequate public input or environmental review.

Indigenous and environmental groups filed a lawsuit late last year against the U.S. State Department and Secretary of State John Kerry in federal district court. Hearings start in Minneapolis on Thursday.

“Plaintiffs’ members face increased risk of harm to their health, recreational, economic, spiritual and aesthetic interests as a result of the State Department’s decision to allow projects with significant environmental impacts to proceed without fully analyzing and considering the impacts,” the groups said in a complaint filed in February.

At issue are a pair of Enbridge (TSX:ENB) oil pipelines between Hardisty, Alta., and Superior, Wisc.: Line 3 and Line 67, also known as Alberta Clipper.

Both pipelines have presidential permits, the same crucial approval for cross-border infrastructure that TransCanada Corp. (TSX:TRP) has been painstakingly trying to obtain for its Keystone XL project since 2008.

The two sides disagree over whether it’s necessary to go through that process again if more crude is to flow through those lines.

“Enbridge is operating its pipelines consistent with the presidential permits and other permits that it holds for Lines 3 and 67, while meeting its responsibility and obligations to serve its shippers’ needs,” said Enbridge spokesman Graham White in an email.

In court documents, the defendants say the claims “lack merit” and ask the court to “dismiss the complaint in its entirety with prejudice.”

In early 2014, Enbridge announced it would be replacing Line 3 in its entirety and idling the old pipe, deeming that was a better option than fixing the whole 47-year-old line. At $7.5 billion, it would be the biggest project in Enbridge history.

In court filings, the defendants describe the Line 3 replacement as a “maintenance-driven” project, while the plaintiffs say Enbridge is aiming to build a whole new pipeline that should be subject to a full State Department review.

The upgrade will enable the line to pump a maximum of 760,000 barrels per day, up from the current 390,000, according to Enbridge’s own engineering analysis.

Meanwhile, Enbridge is aiming to expand Line 67 from 450,000 barrels a day to 800,000 barrels a day. The plan does not entail laying down any new pipe; rather, capacity is to be boosted by adding pumping horsepower.

Enbridge obtained a presidential permit in 2009 before starting up the first 450,000-barrel-per-day phase of the line, but the State Department says it needs to amend its environmental review before allowing the expansion to go ahead. That process is taking longer than Enbridge anticipated.

In the interim, Enbridge has conceived a workaround that opponents have derided as a “switcheroo.” It involves moving oil from Line 67 to Line 3 and back again through interconnections on either side of the border.

The plaintiffs include the White Earth Nation, an Ojibwe reservation in northern Minnesota; Honor the Earth, an environmental group based on the White Earth Nation; Indigenous Environmental Network; Minnesota Conservation Federation; MN350; Center for Biololgical Diversity; Sierra Club and National Wildlife Federation.

Winona LaDuke, executive director of Honor the Earth, said opponents resorted to court action because “Enbridge and the State Department haven’t listened to anything else.”

“If Enbridge would (obey) the laws of this country and the laws of our tribe, then we would not be in court.”

Follow @LaurenKrugel on Twitter

Enbridge Keystone XL TransCanada

Follow BOE Report
  • Facebook
  • X
  • LinkedIn

Sign up for the BOE Report Daily Digest E-mail

Successfully subscribed

Latest Headlines
  • Iran will halt attacks as long as US maintains pause, Iranian source says after Trump calls off strikes
  • Five things to watch for in the Canadian business world in the coming week
  • Iran war spreads to Red Sea and Caspian, Gulf quiet as US forgoes strikes
  • Missiles targeting Saudi oil refineries shot down, sources say
  • Kuwait’s KPC signs $16 billion lease and leaseback deal for oil pipeline network

Return to Home
Alberta GasMonthly Avg.
CAD/GJ
Market Data by TradingView

    Report Error







    Note: The page you are currently on will be sent with your report. If this report is about a different page, please specify.

    About
    • About BOEReport.com
    • In the News
    • Terms of Use
    • Privacy Policy
    • Editorial Policy
    Resources
    • Widgets
    • Notifications
    • Daily Digest E-mail
    Get In Touch
    • Advertise
    • Post a Job
    • Contact
    • Report Error
    StackDX
    • BOE Report Jobs
    • StackDX Intel
    © 2026 Stack Technologies Ltd.