Court ruling in Keystone XL case is another blow against big U.S. natgas pipes

May 29, 202010:21 AM Reuters0 Comments

Canceled Keystone XL pipeline extension being laid

The two biggest U.S. natural gas pipelines under construction are likely facing more delays after an appeals court ruling against the Army Corps of Engineers, energy analysts said.

The Trump administration has pressed ahead with new pipeline construction but several projects have been stalled by successful legal challenges saying the administration is not applying careful regulatory scrutiny.

Last month, a Montana judge ruled the Army Corps authorized permits to cross streams without properly consulting other federal agencies on endangered species. Rather than limit its ruling to the Keystone XL crude pipeline case before the court, the judge questioned the Army Corps’ method of authorizing stream crossing under the entire National Permit 12 program.

The U.S. Ninth Circuit Court of Appeals on Thursday left that ruling in place, which will likely prevent Keystone and other pipelines from using Army Corps’ stream crossing permits until the appeals court decides in early 2021, the analysts said.

It means the two biggest gas pipes under construction – Dominion Energy Inc’s Atlantic Coast and EQM Midstream Partners LP’s Mountain Valley – are likely to be delayed by several more months.

Mountain Valley is not likely to start service until at least the second quarter of 2021, analysts at Height Capital Markets in Washington said on Friday.

“There are too many variables regarding the … recent Ninth Circuit ruling to accurately determine the potential impact to Mountain Valley’s schedule or budget at this time,” said EQM spokeswoman Natalie Cox. The current in-service target for the $5.4 billion West Virginia-Virginia pipeline is still late 2020, she said.

Dominion said it was disappointed in the court’s decision but still planned to complete the $8 billion Atlantic Coast from West Virginia to North Carolina in early 2022, so long as it can cut trees from November to March.

Height Capital analysts, however, said “Dominion will also likely need to push in-service for Atlantic Coast as this decision will impact (its) ability to clear trees.”

Keystone XL

Follow the BOE Report
  • Facebook
  • Twitter
  • LinkedIn
Sign up for the BOE Report Daily Digest E-mail
Latest Headlines
  • Attack on Saudi oil site fuels upward march for crude prices
  • As debate rages over cross-border pipelines, U.S. analysts brace for more oil by rail
  • Innovus convertible frac sleeves deliver impressive bullhead injection distribution in Viking waterflood
  • Volunteering opportunity: Geoscience BC Geothermal Technical Advisory Committee
  • Spartan Delta Corp. announces completion of $45 million bought deal financing

Return to Home
Alberta Gas
CAD/GJ
Market Data by TradingView





    Note: The page you are currently on will be sent with your report. If this report is about a different page, please specify.

    About
    • About BOEReport.com
    • In the News
    • Terms of Use
    • Privacy Policy
    Resources
    • App
    • Widgets
    • Notifications
    • Daily Digest E-mail
    Get In Touch
    • Advertise
    • Post a Job
    • Contribute
    • Contact
    • Report Error
    Featured In
    • CamTrader
    • Rigger Talk
    Data Partner
    • Foxterra
    BOE Network
    © 2021 Grobes Media Inc.